Thursday, 13 March 2014

#NoEstimates and Uncertain Cones

It has been a good month for alienating people... if that can ever be considered a good thing. The first was outing a chap as not really knowing what he was talking about on a certain social media platform. The second was a discussion about #NoEstimates.

I am not going to go over #NoEstimates again, as you can read my initial opinion in a post from last year. The thin slicing of stories really help with this and the concepts in #NoEstimates (which are somewhat shared by ideas like the Elephant carpaccio) show a lot of promise. However, we have to remember that this in itself won't afford continual improvement. That's the missing link.

On a very recent twitter stream, I got into an argument... sorry, passionate debate, with Woody Zuill, a long time advocate of the #NoEstimates movement. One of the things I take issue with is that the term is misleading and has not just zero, but possibly damaging connotations, on the grounds that as people misunderstood agile, they'll misunderstand this term too.

I also reiterated that estimates themselves never killed projects, it was the variance between the estimate and the actual delivery effort that killed projects. That's actually rather obvious when we step out of the somewhat siloed mindset that we developers often have (and sadly criticise others for).

fig 1 - context of discussion before moving to here


If we're aiming to step up into lean and improve the rate of these tiny deliveries to the point at which they are a true flow (if, mathematically speaking we are aiming to see what happens when 'delta-t' tends to zero) and attain consistency, we need to reduce this variance around tasks (and the flow), which is the reason that #NoEstimates often works in the first place. The truth is you're always going to be delivering thin slices, not a 'zero-effort' task and as such, stats has a huge part to play in that as the variance itself increases by over-unity as the task size increases. So to summarise the agreed points, thin slices = good. Name change #NoEstimates -> #BeyondEstimates also agree.

Effing CHEEK!

*meh*

Teams don't always know the solution or even problem they're trying to solve at the beginning of a project. This introduces huge uncertainty into projects at that point. It is the point that estimates are at their most useless and are as good as guaranteed to be wrong.

As we deliver working pieces of code into production, through small increments ideally (as they naturally have a lower individual variance) then we learn more and more about the environment we're working in, the platform were working on, the problems were trying to solve and crucially, the bit that most teams miss, things about themselves and their performance in that environment.

I mentioned the cone of uncertainty in that twitter storm. The cone of uncertainty basically maps out the levels of uncertainty in projects as they move through delivery cycles. The most obvious and visible part of this is seeing the numbers of spikes reduce (or the effort required for them), as you need less and less to understand the problems that are outstanding in the domain. Granted the cone of uncertainty did exist in ye olde world, but if you follow the cone of uncertainty through the lifetime of the project, you'll very typically see the blue line, which is also matched by the funding in the diagram:

fig 2 - image from agile-in-a-nutshell (incremental funding)


Now, this is fine. You can't do much about uncertainty in itself, aside from reducing it as quickly as possible. So where I agree with Mr Zuill et al is that delivering working software often is a good thing and slicing it up thinly is also a good idea. However, this doesn't change the level of uncertainty or that developers still need to improve to deliver the value, which remember, as an investment, includes their time and remuneration (see ROI and ROR for a financial explanation of why that's the case. It's a crucial business value metric for the product owner and developers in a team who are aiming to be trusted or self-sufficient would do well to remember that. Those who have worked LS or have run their own business will already be well aware of these ).

The comment I was probably most 'insulted' by was:

...Such as delivering early and often."

At this point I wondered whether people think I am some sort of #@&!?!

I replied explaining this goes without saying. Delivering small stories early and often allows you to descend the cone of uncertainty and plateau much faster than you otherwise would, in turn getting to the point where Little's Law kicks in and you attain predictability, which is were #NoEstimates really works but the name totally misses the point of this. Which is why I agree with Zuill's assessment that it should be called #BeyondEstimates.

If you don't know where you are or what direction on that curve you're travelling (it's possible for uncertainty to increase. Ask science) then you really aren't going to make any progress. That's what I think #NoEstimates is missing.

As mentioned, the cone of uncertainty ultimately manifests in agile as an inconsistent flow and cycle time with a significant variance (statistical definition of significance). As you deliver more of these slices faster, you start to reach significance thresholds where the use of a normal distribution starts to become viable (30+ samples ideally) and you can infer statistical significance and hence provide control limits for the team. Again, #NoEstimates works well with this, as these thin slices get you to significance faster.

Flow is a concept that features extremely heavily in queuing theory. The cycle-time and throughput effectively manifest in Little's law's equation, which when applicable, can be used to answer questions like "How much effort is involved in this *thing*". However, when you start, the variance is far too high for Little's law to work effectively or return any meaningful predictive information apart from a snapshot of were you are. There is just too much chaos.

When your flow stabilises, the chaos has eradicated and the uncertainty ratio tends to get much closer to 1, i.e. the ability to track how much effort or how long each of these thin slices takes relative to the other thin slices. It's this relative comparison that then allows the predictability to manifest (lowering the standard deviation and hence variance). This makes Evolutionary Estimation easier because you have only got to think about breaking tasks down into tiny, think slices and this is where this understanding helps this evolution. Go too small, then the overhead of build->test->deploy far outweighs the development costs and in the case of ROR, monetary uncertainty increases again. 

This is something I assume everyone who knows about agile development knows about. Given his response, I am assuming that's not the case. So I am obviously in a different place from 'them' (whoever they are). However, as well as being a good talking point amongst the capable, it also seems to manifest in amateurs who just like to code, which is the same pattern I saw when I first came across XP in 2002.

History repeating itself? I really hope not! So I second Zuill's proposal to change the name to #BeyondEstimates

Signed,


Disgruntled of the web :(

Sunday, 22 September 2013

#NoEstimates

Once in a while I come across a host of different 'fads' which actually have something to them, but are sold as something completely different, often for what I consider are the wrong reasons or focus on the wrong things. This is like Viagra, which was created as something completely different, but has become synonymous with sex, become the butt of jokes and the epitome of junk mail amongst a host of other things. Indeed, back in the day, before people understood agility and as is the case with lean software development today, this was the same. Consider it the same as tech following Gartner's hype curve.

This time round, it is the turn of the 'No Estimates' school.

No estimates is a movement which seems to be sourced in the non-committal Kanban world which people assume to mean that no estimates are given for tasks. This is not actually true. The aim of the group is to move away from the concept of estimation as we know it. This includes the sizing of tasks by story points, and concentrating on counting cards. ThoughtWorks released an e-Book in 2009 about using story cards as a measure of velocity and throughput. I personally take this one step further and prefer to break tasks down into the smallest logical unit with the lowest variance. What I mean by this is that I prefer to play to the human strength of being better able to measure small things than large (in terms of variance of the actual metric from the expected metric).

This means that I personally much prefer to size things in single point items/stories. Larger tasks are then composed of these smaller subtasks, like Kanban in manufacturing composes larger parts from smaller ones. The lower variance means lower delivery risk and lower safety (read inventory) and pushes the team closer to the predictability afforded by Little's law as the safety margin factor to zero.

Why Smaller?

Consider a burn down chart of tasks. The burn down never actually follows the burn down path exactly. The nature of story sizes means that you will have an 8 point task move across the board and completing it will decrement the burn down by a discrete 'block' of points (8 in this case). So the best you can get is a stepped pattern, which in itself makes the variance larger than it needs to if the burn-down rate is taken as the 'ideal' baseline (note, a burn down chart is the 'ideal' model of how the work will decompose).

Why do you care? Because this stepped pattern introduces a variation of its own. This means that some times you will have slack, others you'll be rushing, all during the same project. This is all without the introduction of a variance on the size of the task at hand (as shown my a previous blog post on evolutionary estimation, often points don't actually reflect the relative effort in stories) which in themselves introduce a variance on this variance. The fabricated image below shows the variance on a burn down due to the step and when you consider the variation in the size of one point tasks, bracketed in the time periods at the bottom, this is the second variance due to the timings being out.

fig 1 - Burn down of the variation of both the 'steps' and the
delivery timing for different sized stories. The idealised burn down is shown in red (typical of tools like JIRA Agile).


Note, the blue line shows the top and bottom variance of the actual delivered timing (i.e. the green step function), not against the red burn down line. If the average were plotted on the above, the burn down 'trajectory' would sit above the red line, passing half way through the variation. So as of any moment, the project would look like it would be running late, but may not be. It's harder to tell with the combination of the variance of task size and time per task.

Reducing the size of stories to one point stories gets you closer and closer to the burn down line and gives you the consistent performance of the team, which will have a much narrower variance simply because of the use of a smaller unit of work per unit of time. The following example, which is the same data as in fig 1, just burning down by one point, shows that for this data, the variation is reduced, simply by making the story points a consistent size.

fig 2 - 1-point burn down chart showing shorter variation


The reduction in variation is 12 percent, which by proxy, increases the certainty, simply by sizing the tasks per epic differently. This reduction in variation reduces the variance around the throughput (which is story points per unit sprint/iteration). The only 'variable' you then have to worry about is the time a story point takes, which then simply becomes your now relatively predictable cycle time. 

The key with No Estimates, as should be apparent by now, is that it is an absolute misnomer.  They do estimate, but not as a forecast with many variables.

Why does this work?

There is a paper and pen game I play when explaining variance to people. I do this twice and for each go, I draw one of two lines. Firstly one short and one long, on a piece of paper and each time ask Joe/Jane Bloggs to estimate the size of the two lines on the paper. I then ask them to estimate how many longer lines can fit in the shorter one, by eye only. After all three steps are complete, I get a ruler and measure the lines. Usually, the longer line and combination are significantly off, even if the estimates of the short line is fairly good. Please do try this at home. 


fig 3 - Estimate the size of the smaller and latter, then estimate how many small tasks go into the latter.


As humans, we're rubbish...

...at estimating. Sometimes we're also rubbish at being humans, but that's another story. 

The problem arises because there are three variances to worry about. The first is how far out you are with the shorter line. When playing this game, most people are actually quite good at estimating the shorter line. For say, a 20mm line, most will go between 18mm and 21mm. The total variation is 3mm. That's 15 percent of the length of the line. 

With a longer line of 200mm say, most people are between 140mm and 240mm. A total variation of 100mm which is 50% of the line length. 

When the combination of these errors occurs, it is very rare that they are cancelled out altogether. However, the total error when performing the 20mm into the 200mm line effectively multiplies the error by at least 10 (as you take your smaller line measure by eye and apply it one after the other to measure the longer line, the error adds up) and on top of that, you have the error in estimating the big line, which means the total effect of the variances is a factor of the multiplication of the variance of the smaller line with the larger and not the addition. It's non-linear.

Note, the important thing isn't the actual size of the line. You first draw the line and you don't care how big it is. It's the deviation of the estimate from the actual size of the line that's important.

What's the point?

OK, granted, that joke's getting old. From my previous evolutionary estimation blog post, you can see that estimation is not a super-fast nor simple matter when trying to apply it to retrospective data. Indeed the vast majority of developers don't have the statistical background to be able to analyse the improvements they make to their estimation processes. By contrast, No Estimates aims to do away with the problem altogether by fixing the size of a story to one size. For example, what would have been a three point story in the old(er) world. In a way that's a good thing and intuitively relates better to the concept of a kanban container size, which holds a certain number of stories. In the software world this maps to the idea of an epic, or story with subtasks.

Conclusion, is what you said previously is 'pointless'?

Nope! Definitely not. Makes a good joke heading though.

The previous techniques I have used still apply, as the aim is to match the distribution in exactly the same way, just with one story size as opposed to the many that you have in other estimation techniques. Anything falling outside a normally distributed task could get 'chopped' into several story sized objects, or future pieces of work resized so each subtask is a story.

Just to reiterate, as I think it is worth mentioning again. Projects have never failed because of the estimates. They filed because of the difference between estimated and actual delivery times. That's your variation/variance. Reduce the variation, you increase predictability. Once you increase predictability, speed up and monitor that predictability. Then 'fix it' if it gets wide again. This is a continuous process, hence 'continuous improvement'.